MBP provided owner’s representative services including constructibility review at the 95% stage, procurement phase services including AIA contract document review and Division 1 coordination, construction management services, CPM schedule review, commissioning, and building envelope commissioning services. The project is a 115,000-square-foot, state-of-the-art courthouse that combines the General District Court, Circuit Court, Juvenile and Domestic Relations… Read More
MBP assisted with the facilitation of a value engineering workshop on the expansion of the Honolulu Airport (HNL) to provide a new Interisland Terminal in Honolulu, Hawaii. The New Day Work Program (NDWP), Inter-Island Terminal (IIT), Mauka Extension project is part of a larger Honolulu International Airport, Terminal Modernization Program and involved the construction of… Read More
MBP became involved in the project on behalf of the owner during the reconstruction of the digester area of the Gramercy Alumina Refinery after it was destroyed in a catastrophic explosion involving high-pressure piping and pressure vessels. MBP provided on-site inspection, CPM scheduling, cost to complete estimates, analysis of the actual costs of performance, expert… Read More
MBP provided design development and 100% construction document constructibility review services on the project. Project Infinity is a two-story, 169,280-gross-square-foot administrative and clinical laboratory facility. The facility consists of structural steel frame, elevated concrete deck, architectural pre-cast concrete panels, fixtures, furnishings and laboratory equipment.
MBP provided CPM scheduling services and design, construction, acceptance, and warranty phase commissioning services for the new high school. The project involved the construction of a new, approximately 275,000-square-foot high school situated on 45 acres. The project included the incorporation of design and building practices that enhance the educational environment, energy efficiency, and sustainability of… Read More
In 2019, as a subconsultant to FEA, MBP has assisted with the facility assessments, site investigations, and scoping of deferred maintenance and capital improvement projects at over 31 national parks for over 125 assets across the continental United States, Hawaii, and Alaska. These projects include a mix of facility types, road/street repairs, utility distribution, water/wastewater… Read More
MBP conducted a formal 40-hour value engineering workshop on behalf of Norfolk State University. In addition, MBP provided commissioning services in accordance with the ASHRAE Guidelines and USGBC LEED Energy & Atmosphere 1, Fundemental Commissioning. This project consisted of a new 140,676-square-foot classroom building that included spaces academic and nursing training. The academic spaces for… Read More
MBP performed independent cost estimates on behalf of North Carolina State University under an on-call task-order contract. The projects estimated under this task-order agreement included the 1911 Building, Greek Village Phase I, Partners II, and Thompson Theater. 1911 Building The project consisted of the renovation of an existing 48,500-square-foot building originally constructed in 1911 to include new faculty… Read More
MBP provided CPM scheduling services to ODOT for phase 1 and phase 2 of this design-build project. The project was part of the Cleveland Innerbelt modernization project and involved the construction of a new eastbound I-90 bridge over the Cuyahoga River Valley. This new bridge replaced the exisiting I-90 non-redundant steel cantilevered deck truss with… Read More
MBP conducted a formal 40-hour value engineering workshop utilizing an independent team of architects and engineers. The value engineering study was conducted in accordance with the practices recommended by SAVE International. The Basketball Practice Facility project located at Old Dominion University, is a 23,961-gross-square-foot facility housing the basketball practice and administrative functions for both the… Read More